NEW QUESTION 27
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt of a non-stock item
- B. Goods receipt into unvaluated project stock
- C. Goods receipt into valuated project stock
- D. Recording of external services in the service entry sheet
Answer: B,D
NEW QUESTION 28
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
- A. A header-account-assigned network that is assigned to a sales order item
- B. An activity-account-assigned network that is assigned to a sales order item
- C. A dynamic item processor (DIP) profile with the appropriate settings
- D. Released WBS elements, activities, and/or activity elements
Answer: C,D
NEW QUESTION 29
Where do you maintain the length of the project ID?
- A. Project coding mask
- B. Special characters
- C. Project type
- D. Project profile
Answer: A
NEW QUESTION 30
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Network profile
- B. Network type
- C. Project profile
- D. Parameters for the network type
Answer: D
NEW QUESTION 31
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Item category
- B. Control key
- C. Requirement class
- D. Project profile
Answer: C
NEW QUESTION 32
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.
- A. Material components
- B. Basic dates for activities
- C. Relationships
- D. Internally processed activities
- E. Document information records
Answer: A,C,D
NEW QUESTION 33
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. A subnetwork cannot be defined for a superior subnetwork.
- B. Subnetworks must be scheduled separately from the superior network.
- C. The scheduling type of a subnetwork is always copied from the superior network.
- D. Maintenance orders can be defined as subnetworks.
Answer: D
NEW QUESTION 34
What functionality can you perform with activity elements?
- A. Schedule WBS elements
- B. Assign work centers and capacities
- C. Assign material
- D. Create relationships
Answer: D
NEW QUESTION 35
How can you update the degree of processing for an activity?
- A. By using results analysis
- B. By confirming the activity
- C. By changing the activity
- D. By scheduling the activity
Answer: B
NEW QUESTION 36
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.
- A. The procurement type of the material must be internal.
- B. The exact lot size procedure must be used.
- C. The materials must allow sales order or project stock.
- D. An MRP group must be assigned.
Answer: C,D
NEW QUESTION 37
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter February 10 as fixed date.
- B. Enter an offset of 10 days to the start date of the activity.
- C. Enter 10 days as duration.
- D. Enter an offset of -18 days to the finish date of the activity.
Answer: A
NEW QUESTION 38
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Top-down
- B. Bottom-up
- C. Strict bottom-up
- D. Free planning
Answer: B
NEW QUESTION 39
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.
- A. Automatic activation with the first actual posting
- B. Automatic activation with budget assignment
- C. Background activation (CJBV - Activate Availability Control)
- D. Automatic activation with assignment to an investment program
Answer: B,C
NEW QUESTION 40
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
- A. You can use the same coding mask for standard projects and operative projects.
- B. You can shorten the project mask even when there are existing projects.
- C. You can only use numbers for a project coding mask definition.
- D. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
Answer: A,D
NEW QUESTION 41
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing material availability
- B. Missing authorizations to release material components
- C. Missing reservations for material components
- D. Missing budget for material components
Answer: B
NEW QUESTION 42
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Maintenance orders assigned to an activity
- B. Project-relevant purchase orders
- C. Production orders assigned to WBS elements
- D. Capacity requirements
Answer: A,D
NEW QUESTION 43
What could be a reason to use expert mode in the valuation method for results analysis?
- A. Assignments of different accounts for postings to financial accounting
- B. Usage of different line IDs
- C. Billing WBS elements belonging to different company codes
- D. Valuation in different currencies
Answer: A
NEW QUESTION 44
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
- A. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
- B. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
- C. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
- D. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
Answer: D
NEW QUESTION 45
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
- A. Internal orders
- B. Purchase order items
- C. Sales order items
- D. Reservations
Answer: B,D
NEW QUESTION 46
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The material master is set to external procurement.
- B. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
- C. The availability check for material components indicates missing parts.
- D. The material is assigned to the activity as a non-stock material.
Answer: B,C
NEW QUESTION 47
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.
- A. DIP is used to create a quotation.
- B. Material determination is mandatory.
- C. Sales prices are maintained in the DIP profile.
- D. Usage of cost elements is mandatory.
- E. Sources can be based on line items.
Answer: A,C,E
NEW QUESTION 48
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.
- A. Vendor
- B. Service purchase order number
- C. Service specification
- D. Overall limit (maximum value of all unplanned services)
- E. Material master within service specification
Answer: A,C,D
NEW QUESTION 49
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
- A. Company code
- B. Sales organization
- C. Operating concern
- D. Plant
- E. Controlling area
Answer: A,D,E
NEW QUESTION 50
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.
- A. Network header for activity-account-assigned networks
- B. WBS elements
- C. Standard WBS elements
- D. Network activity for activity-account-assigned networks
Answer: A,B
NEW QUESTION 51
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.
- A. Production version
- B. Material
- C. Resource
- D. Location
Answer: C,D
NEW QUESTION 52
......